Subsequently, Kvaerner awarded a contract to Offshore Group Newcastle (OGN) to construct Preassembled units (PAUs) with both free issue main and specialist equipment and internally procured structural and piping materials. The work also included full painting and special fire and heat insulation over the main steelwork and pipelines.
The contract work scope was for a total of 18 PAUs, these ranged from 20 tonne structural pipe racks to three 900 tonne fully equipped and tested PAU compression modules. As all these new PAU units had to integrate fully with the existing plant systems it was critical that the PAUs had a dimensional accuracy to ensure the installation, testing and commissioning plan had no connection problems.
There was a sequential delivery plan which had to be achieved to avoid production problems on the Nyhamna site.
FURTHER PROJECTS SUPPORTED BY IRS
SATURN: MINIMUM FACILITIES PLATFORM PROJECT
MUNRO: MINIMUM FACILITIES PLATFORM PROJECT
VAMPIRE: MINIMUM FACILITIES PLATFORM PROJECT
EUROPA: MINIMUM FACILITIES PLATFORM PROJECT
MALORY: MINIMUM FACILITIES PLATFORM PROJECT
VISCOUNT: MINIMUM FACILITIES PLATFORM PROJECT
SHEARWATER: ACCOMMODATION PLATFORM PROJECT
RHYL FLATS: METEOROLOGICAL MEASURING STATION PROJECT
CARRACK: WELLHEAD PRODUCTION PLATFORM PROJECT
BUZZARD: ACCOMMODATION PLATFORM PROJECT